Modular Construction Cost per Square Foot for Developers in 2026

What a developer actually pays per square foot for modular homes in 2026, what that price includes, and how to turn it into a cost per door you can take to a lender.

A modern two-section modular home with black metal roof and cream siding on a rural lot at golden hour shot on Kodak Portra 400 film with visible grain
On this page

    The short version

    • Delivered and set, modular runs about $85 to $155 per sq ft on the East Coast and $125 to $250 on the West Coast in 2026.
    • The factory price is only one line. Site work, soft costs and loan interest decide your real cost per door.
    • Time is where developers save the most. Homes are built indoors while site work happens, so you carry the land and the loan for fewer months.
    • Repeat plans price better. When the same plan is built across a project, the price is set once instead of rebid on every lot.

    Modular construction cost per square foot in 2026 runs about $85 to $155 on the East Coast and $125 to $250 on the West Coast, delivered and set. That figure covers the home built in the factory, shipped and craned onto your foundation. Your all-in cost per door adds site work, soft costs and financing, and those vary more by site than by home.

    Cost line (per home) What it covers How it's priced
    Modular home, delivered and set Factory build, transport, crane, set crew Per sq ft or per module
    Site work Clearing, grading, foundation, utilities Per lot, local crews
    Soft costs Permits, impact fees, engineering, surveys Per lot or per project
    Finish-out on site Connections between modules, porches, decks, driveways Per home
    Financing Construction loan interest while you build Per month carried

    The per-square-foot ranges come from PERCH's factory pricing in 2026. Everything below the first row depends on your land and your town.

    What the modular price per square foot includes

    A factory's price per square foot isn't a standard unit. Two quotes at the same number can include very different things, so the first job is to find out what's actually in the price.

    Usually included in a delivered-and-set price

    • The finished home sections, built to your state's residential code
    • Interior finishes, fixtures and the appliance package for the chosen finish level
    • Transport from the plant to your site, within the factory's delivery range
    • The crane and set crew on set day

    Sometimes included, so ask

    • Roofing. Some factories finish the roof on site after the set, others ship it ready. One factory quote PERCH received in 2026 included shingling, shipping, set and crane in its delivered price, while its production-only price was about $20 per sq ft lower.
    • Mate-line work. This means the connections where sections meet: finishing the seams, tying in electrical and plumbing, and closing up siding.
    • Porches, garages and decks. These are often built on site.
    • Engineering and state approval fees for your specific plan.

    Almost never included

    • Foundation, utilities and site prep
    • Permits and impact fees
    • Driveways, landscaping and anything outside the home's footprint

    When you compare quotes, line them up item by item. A low price per square foot that leaves out the set crew and the roof can cost more in the end.

    Why prices differ on the East and West Coasts

    The two coasts price differently for reasons that have little to do with the homes themselves. Knowing them helps you set a budget before the first quote.

    Codes and engineering

    West Coast homes, especially in California, must meet seismic and energy rules that add engineering and materials. Coastal Florida has high-wind zones with their own requirements. Each of these pushes the price per square foot up, regardless of the factory.

    Factory density and delivery distance

    The Southeast and Mid-Atlantic have more plants close to more markets, so homes travel shorter distances. Longer hauls cost more, and some sites need special routing for wide loads. Delivery is usually priced by distance from the plant, which is one reason PERCH matches each project to the factory nearest the site.

    Labor and land

    Higher local labor costs show up in set crews, finish work and site work. Land costs don't change the factory price, but they raise the stakes on schedule, because every month you carry expensive land costs more. For the homeowner view and the state detail, see modular home prices by state.

    How to turn price per square foot into cost per door

    Developers underwrite cost per door, not price per square foot. Here's a simple way to build it, using clearly labeled example numbers. Your numbers will differ.

    Step 1: Price the home

    Say you're building 20 homes of 1,600 sq ft on the East Coast at $120 per sq ft, delivered and set.

    1. Home price: 1,600 × $120 = $192,000 per home
    2. For 20 homes: $3,840,000

    Step 2: Add site work and soft costs per lot

    Site work varies the most. Get local bids for:

    • Foundation (slab, crawl space or basement)
    • Water, sewer or septic, electric and gas connections, including tap fees. One Virginia lot PERCH reviewed in 2026 had an $8,700 county water tap fee, plus about the same to run the line across the road.
    • Grading, driveways and erosion control
    • Permits, impact fees, surveys and engineering

    Step 3: Add financing for the months you carry

    This is the line modular changes most. Construction loans averaged an 11.67% effective rate in Q2 20261. As a rough example, carrying $1,000,000 of construction debt at that rate costs about $9,700 a month in interest (1,000,000 × 11.67% ÷ 12). Real draws build up over time, so treat this as an upper-end example.

    Now compare schedules. The average single-family home takes 8.8 months to build once permitted2. McKinsey found that modular construction can cut project schedules by 20 to 50 percent3. On the example above, taking even 3 months out of the schedule is roughly $29,000 less interest per $1 million carried.

    Step 4: Divide by the number of homes

    Add the home price, site work, soft costs and financing, then divide by the number of homes. That's your cost per door, the number your lender and investors will ask for first.

    See your cost per door before you break ground.

    Send us your site plan. We'll match homes to every lot and price each one, delivered and set.

    Send your site plan

    How volume changes modular pricing

    Building many homes changes the math in your favor, but only if the project is set up to repeat.

    Repeat plans

    When the same plan is built again and again, the factory has already engineered it, approved it and learned it. The price is set once. Developers who change plans on every lot give that advantage away. PERCH plans are already priced nationwide, so a project starts from a known number rather than a blank page.

    Order size and timing

    Factories plan production in slots. Ordering several homes at once, or committing to a schedule, gives the plant a reason to sharpen its price. One factory told PERCH in 2026 that it would rather see at least 2 homes ordered at a time, and preferably 3 to 5. Ask each factory how its price changes with order size, and get the answer in writing.

    Capacity

    Popular plants fill up. If a factory's slots are full, your project waits or moves to another plant. Lock your production window early, and know which other plants could build your plan if the first one can't.

    Modular cost per square foot for multifamily

    Apartments and larger multifamily projects follow the same logic, with a different unit of measure.

    Price per module, shown per unit

    Factories build and ship modules, often called boxes. For multifamily, ask for a price per module, then roll it up:

    • Per unit: the modules in each unit type, plus each unit's share of corridor and common-area modules
    • Per gross square foot: the total divided by the building's gross area

    Lines that are separate in multifamily

    • Podium or foundation: often a concrete ground floor built on site
    • Stairs, elevators and common areas: sometimes modules, sometimes site-built
    • Set days: priced per module or per crane day
    • Mate-line and finish work between modules

    For a mid-rise project, the site-built pieces can be a large share of the budget. Get them priced alongside the modules so the comparison with a site-built bid is fair.

    Payment terms: the cost developers miss

    The price per square foot gets the attention, but payment terms can decide whether a project closes.

    Factories often want money before the home ships

    Many plants require most or all of the home's price before shipping. Construction lenders release money in draws after work is done on site. That gap has stopped modular deals that penciled out on cost. For the full picture, see how construction loan draws work for modular.

    How to close the gap

    1. Ask each factory for its exact payment schedule before you compare prices.
    2. Show that schedule to your lender early, and ask how they handle modular draws.
    3. Use milestone payments held for each stage, so the factory can see the money is there and the lender releases it when each stage is done.

    PERCH structures payments around set milestones so the factory, the developer and the lender can each see where the money is.

    How to get an accurate modular quote

    A quote is only as good as the information behind it. Send these up front:

    1. Your site plan, with lot lines, lot sizes and setbacks
    2. The plan set, or the home you want matched: square feet, beds, baths and number of stories
    3. The site address or county, so delivery and code requirements are right
    4. The finish level, standard, mid-range or premium
    5. Your target schedule and the number of homes per phase
    6. Your lender's draw schedule, if you have one

    With those in hand, you can compare quotes on the same terms and avoid surprises after you sign.

    Modular construction cost per square foot: the bottom line

    Modular construction cost per square foot in 2026 runs about $85 to $155 on the East Coast and $125 to $250 on the West Coast, delivered and set. That price is the most predictable part of a project. The rest depends on your land, your town and how long you carry the loan. For developers, the biggest wins come from repeating plans, ordering in batches and taking months out of the schedule.

    Building 5 homes or 500?

    PERCH prices every lot on your site plan, delivered and set, from the factory nearest you.

    Get your lots priced

    Sources


    Frequently asked questions

    What does modular construction cost per square foot in 2026?
    About $85 to $155 per square foot on the East Coast and $125 to $250 on the West Coast, delivered and set. Site work, soft costs and financing come on top.
    Is modular construction less expensive than site-built for developers?
    Often, mostly because of time. The home is built indoors while site work happens, which shortens the schedule and cuts the months of loan interest you carry. The factory price alone may be close to a site-built bid, so compare the full cost per door.
    What's included in a modular price per square foot?
    Usually the finished home sections, interior finishes, transport and the crane set. Roofing, mate-line work, porches and engineering vary by factory. Foundation, utilities, permits and site work are almost never included.
    Why is modular more expensive on the West Coast?
    Seismic and energy rules, higher labor costs and fewer plants near some markets all push prices up. In California, engineering and code requirements add the most.
    Do modular factories give volume pricing?
    Many prefer orders of several homes at a time and price repeat plans better, because the engineering and approvals are already done. Ask each factory how its price changes with order size.
    How do you price modular apartments?
    Ask for a price per module, then roll it up to a cost per unit and per gross square foot. Price the podium, stairs, elevators and site-built common areas separately.
    When do modular factories need to be paid?
    Many factories want most or all of the home's price before it ships. Check the schedule against your lender's draws before you sign, and use milestone payments held for each stage where you can.
    How do I get an accurate modular quote?
    Send your site plan, the plan or home you want, the site location, finish level, schedule and your lender's draw schedule. The more complete the package, the closer the quote is to your final cost.
    Share

    Join the conversation

    Comments

    Reader questions get answered. Real names and a working email — that's it.

    For developers

    Send us your site plan.

    We fit a home to every lot and price each one, delivered and set.

    Get your lots priced