How Construction Loan Draws Work for Modular Homes

Construction loans pay out in draws after work is done on site. Modular factories want to be paid before the home ships. Here is how that gap works, and how developers close it.

A modern two-section modular home with black metal roof and cream siding on a rural lot at golden hour shot on Kodak Portra 400 film with visible grain
On this page

    The short version

    • Construction loans pay in draws, released after an inspection confirms each stage is done on site.
    • Modular factories get paid earlier, often in stages before and during production, with most of the money due before the home ships.
    • The real problem is collateral. Until the modules leave the factory, lenders can't easily secure what they're paying for, so many treat it as risk.
    • The fix is a draw schedule built for modular: factory milestones lined up with the loan, funds held for each stage, and proof of progress from the plant.

    Construction loan draws for modular homes work differently from a site-built schedule. A lender usually releases money only after an inspector confirms work on the site. A modular factory needs money before and during production, because the home is built off-site. Developers close the gap by lining up the factory's payment milestones with the loan's draw schedule before signing either contract.

    Stage Site-built draw Modular reality
    Before construction Land, plans, permits Factory often wants a commitment payment months ahead
    Foundation Paid after inspection Paid after inspection (same)
    Framing and structure Paid as walls and roof go up Built in the factory, often paid as modules start and finish
    Delivery and set Not applicable Final factory payment, often at transport and set
    Finish and completion Paid as trades finish Site finish work (connections, porches, driveways)

    How a construction loan draw schedule works

    A construction loan doesn't hand you the full amount on day one. The lender releases it in pieces, called draws, as the project hits set milestones.

    The basic cycle

    1. The builder or developer requests a draw for completed work.
    2. The lender sends an inspector (or reviews photos and invoices) to confirm the work is done.
    3. The lender updates the title check to make sure no new liens have been filed.
    4. The lender releases the money, often holding back a percentage as retainage until the end.

    You usually pay interest only on the money drawn so far, which is why draws exist: they keep interest low until the money is needed.

    A typical site-built draw schedule

    Site-built draw schedules track physical progress on the lot: foundation, framing, roof and windows (the home "dried in"), mechanical rough-ins, drywall, and final completion. Each draw follows work the inspector can see and touch on site. That's the assumption modular breaks.

    Why modular homes don't fit a standard draw schedule

    With modular construction, most of the home is built somewhere other than the land the loan is secured against. That changes when money is needed and what the lender can see.

    Factories are paid on a different clock

    Researchers at the National Renewable Energy Laboratory and the University of Nebraska interviewed seven modular manufacturers and three lenders about how modular projects get paid1. They described a typical factory payment ladder:

    1. 5% with a letter of intent, about six months ahead, nonrefundable
    2. 25% for materials, about three months ahead
    3. About 30% as each module starts production
    4. 30% to 35% as each module is completed
    5. The final 5% at transport and set

    That study looked at a 200-unit multifamily project, so the exact percentages won't match every single-family deal. The pattern holds, though: most of the factory's money is due before the home reaches your land. Some factories go further and require full payment before shipping.

    Factories don't accept retainage

    Lenders often hold back a percentage of each draw until the end of a job. The NREL study found manufacturers act as suppliers, not subcontractors, so they generally refuse retainage on the work they build. Retainage gets held only on the site-built portion1.

    The collateral problem

    This is the core issue. Until modules leave the factory, the materials typically belong to the manufacturer, not the developer, and they sit on the factory's property, not the lender's collateral. The NREL report found lenders tend to treat that factory work as unsecured and underwrite it against the developer's own credit. On the project they studied, that meant lower loan-to-cost, higher blended interest and about 30% more developer equity, with a large share due months before construction started1.

    Get a price your lender can underwrite.

    Send us your site plan. Every home priced, delivered and set, with a milestone payment schedule.

    Send your site plan

    What a modular-ready draw schedule looks like

    A draw schedule that works for modular matches the factory's milestones to the loan's releases, and gives the lender proof at each step.

    Line up the milestones before you sign

    Get the factory's payment schedule in writing first. Then build the loan's draw schedule around it:

    1. Commitment or materials payment: often funded from developer equity, since the lender has nothing to inspect yet
    2. Foundation and site work: standard on-site draws, inspected as usual
    3. Factory production milestones: released on proof from the plant (photos, plant inspection reports, third-party inspector sign-off)
    4. Delivery and set: released when the home is on the foundation
    5. Site finish and completion: standard on-site draws, with retainage held here

    Hold funds for each stage

    The cleanest way to bridge factory timing and lender rules is to hold money for each milestone in an account neither side controls alone. The factory can see that the money is there before it builds. The lender releases it only when the stage is proven. The developer avoids fronting cash early. PERCH structures payments this way, around set milestones, so the factory, the developer and the lender can each see where the money is.

    Give the lender proof from the plant

    Lenders release draws on evidence. For factory stages, that means:

    • Production start and completion dates for each module
    • Photos or video walkthroughs from the plant floor
    • Plant inspection records and the state approval label for each module
    • A bill of lading or delivery record when the home ships

    The more of this a lender can see, the less the off-site work looks like unsecured risk.

    A real example: when the draws don't line up

    In 2026, a homeowner's USDA-backed deal in Virginia stalled for exactly this reason. The lender allowed only a few draws, including one for the lot. The factory wanted its money before shipping, with no exceptions. The home made sense on price, but the payment timing never matched, and the deal didn't close.

    The lesson for developers is simple: the lowest quote isn't always the one that closes. The one that closes has a payment schedule your lender can fund. Ask for that schedule before you compare prices. For what the home itself costs before any of this, see modular home prices by state.

    Questions to ask your lender about modular draws

    Not every lender handles modular the same way. Ask these before you commit:

    1. Have you financed modular before? How many projects, and in which states?
    2. Can you fund a factory milestone before delivery? If so, what proof do you need?
    3. Will you release a draw into a held account that pays the factory when a stage is proven?
    4. How many draws will you allow, and what does each inspection cost? More draws can mean more inspection fees.
    5. Where do you hold retainage? The answer should be the site-built work, not the factory work.
    6. What loan-to-cost and equity do you require for the off-site portion?
    7. Do you offer construction-to-permanent loans for 1 to 4 unit homes, and business-purpose construction loans for developers?

    Questions to ask the factory

    • What is your full payment schedule, and which payments are refundable?
    • When does ownership of the modules transfer to the buyer?
    • What proof can you provide at each stage (photos, inspection reports, production dates)?
    • Will you accept payment from a held account released on milestones?
    • How long is a price locked, and what happens if the production slot moves?

    The NREL study found fixed prices often lock three to six months before production1. That's one of modular's real financing advantages: the lender sees a firm number early.

    Financing gaps that still exist

    Modular financing is improving, but some pieces are still missing.

    No standard bridge for factory payments

    The NREL report notes that HUD's Off-Site Construction Roadmap calls for a bridge-funding vehicle for factory deposits, and that one doesn't exist yet1. Today the workaround is usually developer equity or a local lender who already understands modular.

    Some states are moving first

    The same report points to Colorado as an exception, with low-rate financing for off-site housing through state programs1. Check your state housing finance agency for programs that support factory-built housing.

    How construction loan draws work for modular: the bottom line

    Construction loan draws for modular homes work when the factory's payment schedule and the loan's draw schedule are designed together. Most factory money is due before the home ships, so plan for it with equity, a lender that funds factory milestones, or funds held for each stage and released on proof. Get both schedules in writing before you compare prices, because the deal that closes is the one with payment timing that lines up.

    Building more than one home?

    PERCH prices every lot on your site plan and structures payments around set milestones your lender can follow.

    Get your lots priced

    Sources


    Frequently asked questions

    How do construction loan draws work?
    A construction loan releases money in stages, called draws, as the project hits milestones. The lender usually inspects the work and checks the title before each release, and you pay interest only on what's been drawn.
    Why are modular homes harder to finance with a construction loan?
    Most of a modular home is built off-site, and the factory wants payment before and during production. Lenders usually release money only for work they can inspect on their collateral, so the timing and security don't line up.
    When do modular factories need to be paid?
    Many follow a ladder: a commitment payment months ahead, a materials payment, payments as modules start and finish, and a final payment at delivery and set. Some require full payment before shipping.
    Do modular manufacturers accept retainage?
    Generally no. Research from NREL found manufacturers act as suppliers and refuse retainage on factory work, so retainage is held on the site-built portion instead.
    Can a lender fund a modular draw before the home is delivered?
    Some can, with proof of production such as photos, plant inspection reports and third-party sign-off. Ask before you commit, and get the process in writing.
    What is a construction-to-permanent loan for a modular home?
    It's one loan that funds construction through draws, then converts to a regular mortgage when the home is complete. It's common for 1 to 4 unit homes on owned land with a permanent foundation.
    How many draws does a modular construction loan have?
    It varies by lender. A modular schedule often has fewer on-site draws and adds factory milestones. Each draw can carry an inspection fee, so fewer, well-timed draws can cost less.
    How can developers avoid fronting cash to the factory?
    Line up the factory's milestones with the loan before signing, ask the lender to fund factory stages on proof, and use funds held for each stage that release only when the work is done.
    Share

    Join the conversation

    Comments

    Reader questions get answered. Real names and a working email — that's it.

    For developers

    Send us your site plan.

    We fit a home to every lot and price each one, delivered and set.

    Get your lots priced